Projects

Skip past slider
Project Status In Progress
Project Dates March 2024 - December 2026
Location Brunswick, between Sydney Road and Cameron Street
We’re upgrading the Brunswick Tram Depot to support the addition of larger trams to the fleet, more trams in the depot and to improve accessibility and safety.
Project Status 
Project Dates These works have been cancelled
Location Flinders Street and St. Kilda Road- Works Cancelled
Project Status In Progress
Project Dates February 2026 - January 2027
Location Port Melbourne
We're increasing the power supply to the tram network in Port Melbourne by building a new substation in the rail reserve near the tram line and Bridge Street.
Project Status Completed
Project Dates 10pm, Friday 10 April to 4.30am, Monday 13 April
  • 48
  • 75
Location Bridge Road, Richmond
We’re completing re-surfacing works of the tram reserve along Bridge Road between Punt Road and Church Street, Richmond. 
Project Status Completed
Project Dates Sunday 15 to Thursday 26 February 2026
  • 86
  • 96
Location Bourke and Spencer streets Melbourne
Project Status Completed
Project Dates Friday 14 November to Monday 1 December 2025
  • 57
Location Union and Epsom roads, Ascot Vale
Project Status Completed
Project Dates Monday 6 October to Monday 27 October 2025
  • 19
  • 57
  • 59
Location Victoria and Elizabeth streets, Melbourne
Victoria Street, between Bouverie and Peel streets. Elizabeth Street, between Therry and Queensberry streets.
Project Status Completed
Project Dates Monday 11 August to Monday 15 September 2025
  • 59
Location Matthews Avenue Airport West
Upgrade the tram poles and overhead tram wires along Matthews Avenue, Airport West.
Project Status Completed
Project Dates Sunday 10 August to Thursday 21 August 2025
Location Montague Street, South Melbourne
Replacing the northern crash protection beam at the Montague Street Bridge.
Project Status Completed
Project Dates Sunday 15 June to Monday 7 July 2025
  • 86
Location Plenty Road and Tyler Street Preston
Works to reinstate tram Stop 52
Project Status Completed
Project Dates Monday 28 April to Monday 16 June 2025
  • 1
  • 3
  • 5
  • 6
  • 16
  • 64
  • 67
  • 72
Location St Kilda and Domain roads, Melbourne
Overhead works in Domain and St Kilda roads
Project Status Completed
Project Dates Monday 19 May to Wednesday 28 May 2025
  • 75
Location Burwood Highway, Burwood East
Installing reinforced track foundations at the site access of the Suburban Rail Loop (SRL) Track maintenance and renewal works in the tram reserve on Burwood Highway
Project Status Completed
Project Dates Monday 24 February to Monday 3 March 2025
  • 96
Location St Kilda Light Rail corridor
Maintenance works in the St Kilda Light Rail corridor between Whiteman Street, South Melbourne and Fitzroy Street, St Kilda.
Project Status Completed
Project Dates Early Feburary 2018
Location South Melbourne
Park Street Tram Stop
Project Status 
Project Dates Monday 25 March to Monday 8 April 2004
  • 59
Location Matthews Avenue, Airport West
The Department of Transport and Planning and Yarra Trams regularly carry out maintenance and renewal works across the network to improve operations and passenger experience. We upgraded some of the poles and tram powerlines along Matthews Avenue in January. To continue to deliver safe and reliable tram services to the area, we need to upgrade the remaining poles and tram powerlines. Where? Works will happen in the tram reserve along Matthews Avenue, between Fullarton Road and Hood Street, Airport West. When? Works will happen in the tram reserve along Matthews Avenue, between Fullarton Road and Hood Street, Airport West. What is happening? – Setting up work areas including traffic management. – Locating underground services and installing conduits and cables. – Removing old and installing new tram powerlines and poles. – Reinstating the works area. What to expect? – Vehicles, machinery, and contractors on site. – Mostly low to medium levels of noise. High levels of noise are expected when we are removing poles. – English Street off-ramp will be closed from 10pm to 5am during Stage 1 and Stage 2 of the works. – Temporary removal of adjacent on-street parking along Matthews Avenue. – There will be service changes to Tram Route 59 during Stage 1 and Stage 2 of these works. Visit: yarratrams.com.au/service-changes Businesses located around the works area will remain open during the works. Please continue to support your local businesses during these essential infrastructure works. Please follow signage and traffic management around the work zone and allow extra time when planning your journey. Works are dependent on weather and ground conditions and subject to change. We appreciate your patience while these works are completed
Skip before slider